Change Request Process Flow (Alternate Version)

This is the text based version of Change Request Process Flow.

Standard Change

StageChange TaskChange ApprovalPerformed by
1Request for Change Logged Any OCIO Team Member
2Review RFC Task Change Coordinator
3 Authorized to Build, Test and ReleaseChange Coordinator
4Build, Test and Release RFC Task Any OCIO Team Member
5Post Implementation Review Change Coordinator

RISK Level: Minimum

General Definition:

  • Low risk and no impact planned during the change period
  • Process is repeatable (process must be successfully repeatable)
  • All changes previously considered to be routine
  • Approved to this status in advance by CAB

Minimum lead time of the Request to Authorize for Release:
One business day unless otherwise define for each Standard Change upon initial approval.

Minor Change

StageChange TaskChange ApprovalPerformed by
1Request for Change Logged Any OCIO Team Member
2Review RFC Task Change Coordinator
3 Authorized to Build?Change Coordinator
4Build RFC Task Any OCIO Team Member
5 Authorized to Test?Change Coordinator
6Test RFC Task Any OCIO Team Member
7 Authorized to Release?Change Manager
8Release RFC Task Any OCIOTeam Member
9Post Implementation Review Change Coordinator

RISK Level: Low

General Definition:
Combined Risk & Impact Ranking <8

Risk Factors

  • Experience baseline moderate
  • Not Complex
  • No Planned Service Outage
    or
    Any Planned Service Outage must be contained within the Maintenance Window and have very little risk of additional user impact during or after the change.

Impact

  • More than 1 user affected

Minimum lead time of the Request to Authorize for Release:
3 business days before the target implementation date

Major Change

StageChange TaskChange ApprovalPerformed by
1Request for Change Logged Any OCIO Team Member
2Review RFC Task Change Coordinator
3 Authorized to Build?Change Coordinator
4CAB Review Change Advisory Board
5Build RFC Task Any OCIO Team Member
6 Authorized to Test?Change Coordinator
7Test RFC Task Any OCIO Team Member
8 Authorized to Release?Change Manager
9Release RFC Task Any OCIO Team Member
10Post Implementation Review Change Coordinator

RISK Level: High

General Definition:
Combined Risk & Impact Ranking ≥8

Risk Factors

  • Experience baseline low or failed in past
  • Very Complex
  • Planned Service Outage or the risk of user impact during the change (i.e. high risk during or after the change)
  • Difficult to fully test
  • Difficulty to back out

Impact

  • Extensive/Widespread cessation of core service to the business
  • 2 Significant/Large multiple users affected

Minimum lead time of the Request to Authorize for Release:
As soon as Change is known and/or has received management support decision (Between Initiation and Planning phases of project) must include 2 CAB meetings prior to release.

Urgent/Emergency Change

StageChange TaskChange ApprovalPerformed by
1Request for Change Logged Any OCIO Team Member
2Review RFC Task Change Coordinator
3 Service Owner Authorization?Service Owner
4 SLT AuthorizationSLT Member
5 Authorized to Release?Change Manager
6Build RFC Task Any OCIO Team Member
7Test RFC Task Any OCIO Team Member
8Release RFC Task Any OCIOTeam Member
9Post Implementation Review Change Coordinator

RISK Level: Highest

Emergency Change resolves a Priority 1 Incident (may be completed in retrospect), or a Priority 2 Incident.

Urgent Change is any change where business need does not allow for it to be scheduled as a Normal Change.

Minimum lead time of the Request to Authorize for Release:
As Soon as Possible