Latest Workday Implementation Freeze Dates for December and January
The online Workday Calendar, provided by the Enterprise Project, shares a full listing of deadlines and system freeze dates as part of the move to Workday. Below is a listing of deadlines highlights happening from December 29 through January 8, 2021.
December 29:
- Last day for units to approve eRequests to reallocate credit card charges
December 30:
- Last day to approve pending requisitions and purchase orders
- Last day to approve manual invoices
- Last day to submit bill-only requisitions
- Last day to resolve match exceptions
December 31:
- Last Day for access to production PeopleSoft (except for users performing GL close activity)
- Last day to make deposits in PeopleSoft
- Last day for central finance users to update PeopleSoft assets
- Last day for AR to collections cutoff in SIS
- Last day to approve procurement, travel, expense cost transfers
- Last day to approve expense transfers (Grants)
January 2:
- Last day to submit and approve time in eTimesheet
January 3:
- Workday HR and Payroll go-live
January 4:
- Final bank statement loaded to SunGard for 12/31 statement
- Last day to submit OBA
- Last day for "prepaid" in PeopleSoft for FY21 Period 6 ("utilization", needed to stop sponsor billing)
January 5:
- Last day to submit IDB
January 7:
- Workday Finance and Supply Chain go-live
January 8:
- Last day for users to access PeopleSoft Finance (Except for Central Users performing final FY21 Period 6 Close Activities) and eMaterials